- Project managed the design, procurement, construction and commissioning of Continuous miner, Shuttle Car, LHD, Substation, DCB, Feeder and personnel transport.
- Project value : $20 Million.
- Project delivered ahead of schedule (8 weeks)and $1 Million under budget.